Construction Management

201) In the time-cost optimization using CPM, the crashing of the activities along the critical path is done starting with the activity having

Discuss in Comment

least cost slope

202) Which of the following is a dummy activity?

Discuss in Comment

Await the arrival of concrete material

203) Total cost is

Discuss in Comment

direct cost + indirect cost

204) Outage loss plus overheads is equal to

Discuss in Comment

total cost

205) Which of the following is not related to cost slope?

Discuss in Comment

slack

206) Crashing to the project means

Discuss in Comment

reducing the time of completion by spending more resources

207) resource smoothening means

Discuss in Comment

adjustment of resources to have the least variations

208) Direct cost of a project is due to

Discuss in Comment

cost of materials and wages of labour

209) Total project cost

Discuss in Comment

initially reduces and then increases with increase in time

210) Pick up the correct statement from the following :

Discuss in Comment

all the above

Subject Notes

Objective Box

PSC ADVERTISEMENT

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2024 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us