211) Identify the odd man out

Discuss in Comment

Mix concrete

212) which would represent the most likely time estimate.

Discuss in Comment

the time the activity would most often require if normal conditions prevail

213) The optimistic time estimate represents

Discuss in Comment

the shortest time required to complete the activity under favourable conditions

214) which would represent the pessimistic time estimate.

Discuss in Comment

none of the above

215) Which of the following earth moving machines has the shortest cycle time?

Discuss in Comment

Dipper shovel

216) Which of the following excavators is most suitable for digging under water?

Discuss in Comment

Drag line

217) For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

Discuss in Comment

Moist loam

218) For a given size of bucket, the ideal output of a dragline will be least in

Discuss in Comment

Wet sticky clay

219) Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?

Discuss in Comment

Earth

220) Which of the following surfaces will give highest rolling resistance for a , rubber tyred vehicle?

Discuss in Comment

Loose sand

Subject Notes

Objective Box

PSC ADVERTISEMENT

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2024 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us