The direct cost corresponding to the completion of an critical activity within the given time in order to maintain the critical path not disturbed is

Discuss in Comment

Updated cost

Objective Box

PSC ADVERTISEMENT

CIVILBOSS is a free education & learning platform, for the global community of civil engineering students and working professionals, where you can practice multiple choice questions & answers (MCQs), Study Notes, tutorials, Civil Engineering PSC Old Question for Various Level, PSC Exam Crack, Short Question & Answer for Related Particular Topic and Many More. It covers your one-stop destination for job exam preparation with daily practice MCQ and notes.

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2026 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us

Tweet
Share
Share
Pin