Civilboss MCQS (4)

101) The amount included in the estimate and BOQ for specialized works to be done for unknown details at the time of the preparing estimate is

Discuss in Comment

Provisional sum

102) Detailed estimate is accompanied with

Discuss in Comment

Drawing, Design and calculation

103) The quantities of wood work in a door frame having clear opening in the wall is 7 feet by 4 feet and choukats are 4 inch by 3 inch. The end of horizontal choukats projects 6 inch horns on each side into the wall is

Discuss in Comment

2 cubic feet

104) The floor area includes the area of the balcony up to

Discuss in Comment

25%

105) The most efficient channel section for open channel flow is

Discuss in Comment

rectangular

106) For a population Growth higher than 2% per year design period off a water supply scheme normally taken is

Discuss in Comment

10 years

107) Number of vehicles occupying a road line of unit length at certain time is

Discuss in Comment

traffic density

108) Which document is not necessary for preparing the cost estimate of a construction project

Discuss in Comment

bar chart

109) Critical path

Discuss in Comment

is always longest

110) Pavement width formation width, surface characteristics and camber are termed as

Discuss in Comment

cross section elements

Subject Notes

Objective Box

PSC ADVERTISEMENT

CIVILBOSS is a free education & learning platform, for the global community of civil engineering students and working professionals, where you can practice multiple choice questions & answers (MCQs), Study Notes, tutorials, Civil Engineering PSC Old Question for Various Level, PSC Exam Crack, Short Question & Answer for Related Particular Topic and Many More. It covers your one-stop destination for job exam preparation with daily practice MCQ and notes.

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2026 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us