141) The independent float affects only

Discuss in Comment

the particular activity involved

142) Whenever an activity has zero total float, then

Discuss in Comment

free float and independent float both must be zero

143) In PERT analysis, the time estimates of I activities and probability of their occurrence follow

Discuss in Comment

β- distribution curve

144) Expected project duration generally I follows

Discuss in Comment

normal distribution curve

145) The area under the β – distribution curve 13 divided into two equal parts by

Discuss in Comment

expected time

146) Select the incorrect statement.

Discuss in Comment

none of the above

147) Select the incorrect statement.

Discuss in Comment

Start float and finish float need not be equal

148) Select the incorrect statement.

Discuss in Comment

Critical activity is the one for which free float is zero

149) The process of incorporating changes and rescheduling or replanning is called

Discuss in Comment

updating

150) Interfering float is the difference between

Discuss in Comment

total float and free float

Subject Notes

Objective Box

PSC ADVERTISEMENT

CIVILBOSS is a free education & learning platform, for the global community of civil engineering students and working professionals, where you can practice multiple choice questions & answers (MCQs), Study Notes, tutorials, Civil Engineering PSC Old Question for Various Level, PSC Exam Crack, Short Question & Answer for Related Particular Topic and Many More. It covers your one-stop destination for job exam preparation with daily practice MCQ and notes.

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2026 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us