131) At a work site, statistical quality control of concrete means

Discuss in Comment

applying the theory of probability to sample testing inspection

132) In resources levelling

Discuss in Comment

uniform demand of resources is achieved

133) Select the correct statement.

Discuss in Comment

none of the above

134) Which of the following does not represent an activity?

Discuss in Comment

foundation is being dug

135) Earliest finish of an activity is always

Discuss in Comment

less than or equal to earliest event time of the following node

136) Latest start of an activity is always

Discuss in Comment

greater than or equal to latest event time of preceding node

137) Free float is mainly used to

Discuss in Comment

identify the activities, which can be delayed without affecting the total float of succeeding activity

138) Total float for any activity is defined as the difference between

Discuss in Comment

its latest start time and earlier finish time

139) Free float for any activity is defined as the difference between

Discuss in Comment

its earliest finish time and earliest start time for its successor activity

140) The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

Discuss in Comment

independent float

Subject Notes

Objective Box

PSC ADVERTISEMENT

CIVILBOSS is a free education & learning platform, for the global community of civil engineering students and working professionals, where you can practice multiple choice questions & answers (MCQs), Study Notes, tutorials, Civil Engineering PSC Old Question for Various Level, PSC Exam Crack, Short Question & Answer for Related Particular Topic and Many More. It covers your one-stop destination for job exam preparation with daily practice MCQ and notes.

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2026 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us