91) The occurrence of the starting of an activity is called its

Discuss in Comment

tail event

92) A dummy activity

Discuss in Comment

does not require any resources or any time

93) The probability distribution taken to represent the completion time in PERT analysis is

Discuss in Comment

Beta distribution

94) The float may be defined as the difference between

Discuss in Comment

all the above

95) The total cost versus time curve is

Discuss in Comment

∪-shaped curve

96) Which of the following is a dummy activity?

Discuss in Comment

Await the arrival of concrete material

97) Identify the odd man out

Discuss in Comment

Design completed

98) resource smoothening means

Discuss in Comment

adjustment of resources to have the least variations

99) Negative slack indicates

Discuss in Comment

on schedule condition

100) The optimistic time estimate represents

Discuss in Comment

the shortest time required to complete the activity under favourable conditions

Subject Notes

Objective Box

PSC ADVERTISEMENT

CIVILBOSS is a free education & learning platform, for the global community of civil engineering students and working professionals, where you can practice multiple choice questions & answers (MCQs), Study Notes, tutorials, Civil Engineering PSC Old Question for Various Level, PSC Exam Crack, Short Question & Answer for Related Particular Topic and Many More. It covers your one-stop destination for job exam preparation with daily practice MCQ and notes.

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2026 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us