71) In PERT, the critical path represents the

Discuss in Comment

longest path of the network from the initial to final event

72) Higher standard deviations mean

Discuss in Comment

nothing to do with uncertainty

73) Negative float for any activity means that the activity is

Discuss in Comment

super-critical

74) Zero floats for any activity means that the activity is

Discuss in Comment

critical

75) Positive float for any activity means that the activity is

Discuss in Comment

sub-critical

76) The total float for any activity along the critical path in CPM is

Discuss in Comment

zero

77) Fulkerson’s rule is used for numbering the

Discuss in Comment

events

78) Which of the following is not related to cost slope?

Discuss in Comment

slack

79) In the time-cost optimization using CPM, the crashing of the activities along the critical path is done starting with the activity having

Discuss in Comment

least cost slope

80) Crashing to the project means

Discuss in Comment

reducing the time of completion by spending more resources

Subject Notes

Objective Box

PSC ADVERTISEMENT

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2024 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us