181) A dummy activity

Discuss in Comment

does not require any resources or any time

182) Use of dummies is required for

Discuss in Comment

both (a) and (b)

183) Fulkerson’s rule is used for numbering the

Discuss in Comment

events

184) The time by which the completion of an activity can be delayed without affecting the start of succeeding activities is called

Discuss in Comment

free float

185) When all the paths are arranged according to the descending order of the float, the path which is next to critical path is known as

Discuss in Comment

semi-critical path

186) The total float for any activity along the critical path in CPM is

Discuss in Comment

zero

187) Negative float for any activity means that the activity is

Discuss in Comment

super-critical

188) Zero float for any activity means that the activity is

Discuss in Comment

critical

189) Positive float for any activity means that the activity is

Discuss in Comment

sub-critical

190) Slack is given as the difference between

Discuss in Comment

latest allowable time and earliest expected time

Subject Notes

Objective Box

PSC ADVERTISEMENT

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2024 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us