191) For all the events along the critical path, the slack is

Discuss in Comment

minimum or zero

192) Negative slack indicates

Discuss in Comment

on schedule condition

193) Which of the following is an example of parallel activities?

Discuss in Comment

construction of walls and carpentry work of doors and windows

194) When the events are numbered in a network then the number of the head event of an activity

Discuss in Comment

always larger than the number of the tail event of the same activity

195) Higher standard deviations means

Discuss in Comment

nothing to do with uncertainity

196) Float may be defined as the difference between

Discuss in Comment

all the above

197) Interfering float is the difference between

Discuss in Comment

Total float and free float

198) If the probability factor is zero, the chances of completing the project in scheduled time are

Discuss in Comment

50 %

199) The probability distribution taken to represent the completion time in PERT analysis is

Discuss in Comment

Beta distribution

200) The total cost versus time curve is

Discuss in Comment

∪-shaped curve

Subject Notes

Objective Box

PSC ADVERTISEMENT

"Scientists dream about doing great things. Engineers do them."

Copyright © | 2021 - 2024 | Civil Boss For "MCQ" and Psc Notes. All rights Reserved

Follow us